Illustrative example. This story is based on the kinds of situations we help with. Names, figures and details are examples, not a real client's.

A young couple building their first home in Mount Barker hit an $18,000 variation mid-build. They had kept $15,000 of their savings aside on Jason's advice, queried the variation with the builder, and paid the final $12,000 from that buffer without changing the loan.

$630k
Total project
5
Progress draws
$18k
Variation managed

The situation

This young couple had a combined income of $145,000 and $140,000 in savings, and wanted to build their first home in Mount Barker. They had found a block of land for $240,000 and signed a fixed-price building contract for $390,000 - a total project cost of $630,000.

As first home buyers building a new home, they qualified for the $15,000 SA First Home Owner Grant and paid no stamp duty on the land: RevenueSA's first home buyer relief covers vacant land you build a new home on, which saved them $8,530. They still paid the Land Services SA transfer fee on the land ($2,348), the $204 mortgage registration fee and conveyancing. They had never been through a construction loan before and were unsure how progress payments worked or how to handle unexpected costs.

The challenge

Construction loans are significantly more complex than standard home loans. The loan is drawn in stages as the build progresses - typically at slab, frame, lock-up, fit-out, and completion. Each draw requires an inspection, and the lender needs to approve each payment before funds are released to the builder.

Mid-way through the build, the couple received an $18,000 variation notice from the builder for unexpected site costs - rock removal and additional retaining work required by the sloping block. This was not covered by the fixed-price contract and threatened to blow their budget.

Site costs are one of the most common surprises in new builds. Even with a fixed-price contract, items like rock removal, soil remediation, and retaining walls are often excluded. A good broker will flag this risk before you sign and help you build a contingency into your loan structure.

What Jason did

Jason set up a land and construction loan with a lender on our panel that had a straightforward progress draw process. He suggested they keep $15,000 of their savings out of the deposit as a buffer for site costs. The rest of their savings, less about $4,050 in purchase costs, went into the project with the grant (paid at the first progress payment), and the loan covered the balance: about $494,000, or about 78% of the $630,000 cost.

When the $18,000 variation arrived, the couple asked the builder for an itemised breakdown and, with their independent building inspector, queried two items. The builder reduced the variation to $12,000. Jason checked what the lender needed: a copy of the signed variation and proof the couple could pay it. Because they paid it from their buffer, the loan amount did not change.

Land cost
$240,000
Build contract
$390,000 fixed price
Variation
Reduced from $18k to $12k
Lender
Construction loan, panel lender

The outcome

The couple moved into their new Mount Barker home on time and close to budget. The variation came out of the $15,000 buffer, leaving them $3,000. Total final cost was $642,000 - $12,000 over the original $630,000 budget - with no change to the loan.

Without the buffer, the variation could have meant asking the lender to increase the loan mid-build, which takes time, needs a fresh assessment and is not guaranteed. Planning for site costs before signing made the difference.

The takeaway

Site costs are where new builds most often go over budget. In this example the difference was not a clever negotiation by the broker - it was the $15,000 the couple kept aside before the slab was poured, so a variation did not turn into a new loan application.

Is your situation similar?

Book a chat with Jason or Steve. We will look at your situation honestly and tell you what is possible.

Book a 15-minute chat Call 08 8270 5138

Ready to find the
right loan?

Book a chat with Jason or Steve. No obligation, no fee from us.

Jason Given - Construction lending specialist, Lendology Adelaide
Case study by
Jason Given MFPA
Director & Mortgage Broker - Construction lending specialist